University of California San Diego Thornton Hospital Cardiovascular Center, San Diego, CA

cs_health_thornton.jpg

SCOPE OF WORK

Dynalectric San Diego recently completed work on the UCSD Thornton Hospital Cardiovascular Center. This is a 127,000 square-foot, four-story stand alone hospital. The facility consists of three operating rooms, one hybrid operating room, three catheterization laboratories, two floors of patient beds, a digital radiology center, a CT room, emergency room, pre/post operating day bed area and administrative offices.

The scope of work for Dynalectric San Diego included: total electrical, high-voltage systems, tel-data communications, power generation, lighting control and public address. This project required OSHPD approval and BIM coordination of complex electrical systems.

Dynalectric San Diego utilized integrated project delivery with DPR Construction, and other project partners, to produce the highest quality facility within the time parameters outlined by the owner. This project received LEED Silver status.

HEALTHCARE
 

OPERATING COMPANY:
Dynalectric - San Diego

CLIENT:
DPR Construction, Inc.

ARCHITECT:
RTKL

ENGINEER:
EXP

 

cs_value.gif

 

  case_box_check.gif Total Electrical
  case_box_check.gif High-Voltage Systems
  case_box.gif Fire Alarm and Life Safety
  case_box_check.gif Tele-Data Communications
  case_box.gif Security/CCTV
  case_box.gif Building Automation
  case_box.gif Instrumentation and Control Systems
  case_box.gif HVAC/DDC Controls
  case_box.gif Audio and Video Networking
  case_box_check.gif Power Generation