Teleport Communications, San Diego, CA

cs_com_teleport.jpg

SCOPE OF WORK

Dynalectric Company completed this 26,500 square-foot tenant improvement project for TCG-CERFnet in the San Diego Tech Center. This was a “fast track” project including the installation of a custom 600 kW generator in an outside environment; generator was housed in a special weatherproof enclosure located in the existing loading dock area.

In order to enable proper generator operations, Dynalectric fabricated a steel I-beam “wedge” to level the conditions in the loading dock. Additionally, the scope for this TI included new lighting, electrical service upgrade, life safety, power distribution units and an uninterrupted power system for their global server network.

All of this work was completed by Dynalectric in three months and delivered to TCG-CERFnet on time, based on their re-location leasing arrangements.

COMMERCIAL
 

OPERATING COMPANY:
Dynalectric - San Diego

CLIENT:
Dynalectric Company

ARCHITECT:
The McCulley Group

ENGINEER:
Nutter Electrical Design

 

cs_value.gif

 

  case_box_check.gif Total Electrical
  case_box.gif High-Voltage Systems
  case_box_check.gif Fire Alarm and Life Safety
  case_box_check.gif Tele-Data Communications
  case_box_check.gif Security/CCTV
  case_box.gif Building Automation
  case_box.gif Instrumentation and Control Systems
  case_box.gif HVAC/DDC Controls
  case_box.gif Audio and Video Networking
  case_box_check.gif Power Generation