Qualcomm Tenant Improvement, San Diego, CA

cs_com_qualcom_tenant.jpg

SCOPE OF WORK

This 260,000-square-foot design center tenant improvement consisted of two buildings and was required to adhere to an accelerated schedule, allowing only ten weeks for completion.

Dynalectric’s value on this project was evident in the design/assist effort, along with the necessary construction controls involving timely material delivery, coordination with other trades and implementing extensive scope changes.

The construction drawings were only 60% complete at the start of construction. The second project: Building “T” – was comparable to the design center, with extensive use of cable tray and Isoduct throughout the electronic labs.

This project was built with a very aggressive schedule, with a design that was in constant flux.

COMMERCIAL
 

OPERATING COMPANY:
Dynalectric - San Diego

CLIENT:
Roel Construction

ARCHITECT:
Turpit Partners
Prolect & Associates

 

 

cs_value.gif

 

  case_box_check.gif Total Electrical
  case_box.gif High-Voltage Systems
  case_box_check.gif Fire Alarm and Life Safety
  case_box.gif Tele-Data Communications
  case_box.gif Security/CCTV
  case_box.gif Building Automation
  case_box.gif Instrumentation and Control Systems
  case_box.gif HVAC/DDC Controls
  case_box.gif Audio and Video Networking
  case_box_check.gif Power Generation