707 Broadway, San Diego, CA

cs_comm_707broadway.jpg

SCOPE OF WORK

This 18-story, 176,000-square-foot building and adjacent 12-story, 800-stall parking structure began undergoing a major renovation in April 2001.

The project included renovations of the building’s exterior façade and lobby area, along with substantial upgrades to the building’s interior mechanical systems.

OBJECTIVES / VALUE DELIVERED

  • Quick design turnaround
  • Full budgeting throughout the design process
  • Integration of systems during design
  • Fast track construction
  • Budget control
COMMERCIAL
 

OPERATING COMPANY:
Dynalectric - San Diego

CLIENT:
Ninteman Construction

ARCHITECT:
Cooper Roberts Bennett

ENGINEER:
Michael Wall Engineering

 

cs_value.gif

 

  case_box_check.gif Total Electrical
  case_box.gif High-Voltage Systems
  case_box_check.gif Fire Alarm and Life Safety
  case_box.gif Tele-Data Communications
  case_box_check.gif Security/CCTV
  case_box.gif Building Automation
  case_box.gif Instrumentation and Control Systems
  case_box.gif HVAC/DDC Controls
  case_box.gif Audio and Video Networking
  case_box_check.gif Power Generation